For your information

You are being redirected to one of our divisional subsites which contains more detailed information on the required division. To navigate back to the main Invicta Group site, please click the link found in the footer at the bottom of the page.

Durasteel improves fire safety at UAE's largest mosque

Sheikh Zayed Grand Mosque, Abu Dhabi

Quick Quote

Contact Fraser Shearer Sarun Vysakham Ben Tan Azim Rizvi Anand Raghavan Our USA Office

Home Case Studies Durasteel improves fire safety at UAE's largest mosque

Application

Underground Smoke Extraction Ducts

Fire Rating

1 Hour

Project Duration

9 Months

Company profile

The Sheikh Zayed Grand Mosque is one of the largest mosques in the world, and a major site for both worshippers and tourists in Abu Dhabi. Named after Sheikh Zayed bin Sultan Al Nahyan, the Founder of the United Arab Emirates, the Sheikh Zayed Grand Mosque welcomes up to 55,000 visitors every day, and boasts both the largest hand-woven carpet in the world and one of the largest chandeliers in any mosque.

Operated by Sheikh Zayed Grand Mosque Center, the mosque was built as a centre of learning and a place of cultural exchange between Islam and the wider world. Its structures include an extensive library in the northeast minaret, the main prayer hall (hosting up to 7,000 worshippers), two smaller prayer halls (for men and women respectively), and an elaborate series of illuminated columns and pools.

Project challenge

Invicta was approached by project consultant Parsons Corporation to address issues with the design and operation of the existing GI duct ventilation and smoke extraction system in the basement parking area.

Due to its position below the water table, the existing underground GI duct ventilation system in the basement parking area had become filled with sea water, and had as a result become severely corroded. While a water pump extraction system had been retrospectively installed, this was not enough to mitigate the damage caused by the flooding, and the efficient operation and integrity of the system were being impeded.

As the main contractor on the project, Invicta was tasked with redesigning and improving the fire-rated ventilation and smoke extraction performance of the parking area underneath the mosque. In doing so, we would not only have to replace the existing GI duct system in a way that resolved the water table issue, but also improve its aesthetic appearance within the parking area, and limit disruption to the parking area during construction.

Technical constraints

Where the existing duct system utilised a series of trenches that ran below ground level and were embedded within the concrete slab, the new Durasteel fire-rated duct system would have to run above ground level, utilising the existing space between the building I-girders at ceiling level. This would encompass both fresh air supply and smoke extraction ducts, which would connect to the existing fan system in mechanical rooms located at the far end of the parking area – a process which would require the creation of new wall openings within the structural diaphragm wall to allow the ducts to pass through.

As well as removing and blanking off the existing duct system, the creation of a new above-ground ventilation system would also require extensive rerouting of other critical building services which clashed with the positioning of the proposed new duct system. This included the rerouting of fire sprinklers, cable trays, lights and other utilities.

Installed solution

Invicta designed, supplied, installed, tested and commissioned Durasteel 1-hour fire-rated supply and extract ducts between the structural I-girders, including connections to existing fans in the mechanical rooms. The extraction duct was designed with the addition of high-performance insulation board internally, providing thermal protection to the concrete structure in the event of hot smoke extraction during a fire. The duct system was designed to finish flush with the underside of the I-girders, and painted to match the existing surrounding structure, effectively rendering the duct system invisible to the naked eye.

Invicta also supplied and installed 96 fire-rated metal grilles to the supply and extract ducts, balanced in order to ensure even air distribution and smoke extraction throughout the parking area. 19 new wall openings between the mechanical rooms and car park were also constructed, while the existing GI duct openings were closed off, and 46 existing louver towers were removed.

All existing building services that clashed or conflicted with the proposed duct system were removed, capped and rerouted as required. Finally, Invicta supplied and installed 850m² of curved cladding around the areas where the Durasteel ducts passed under the inverted T-beams. This included 12 illuminated advertising boards that matched the aesthetics of the existing parking area and provided tangible benefits to visitors.

Key benefits

As the main contractor on the project, Invicta successfully designed, supplied and installed the new fire-rated ventilation system in the basement parking area within the given timeframe. As well as drastically improving the life safety of the area for the general public in the event of a fire, the removal and rerouting of old building services and louver towers and the installation of curved cladding and illuminated advertisement boards have significantly improved the aesthetics of the parking area.

End result

 

Share/Like this page

Accreditations & Affiliations

SpecUp - System Specification Wizard

Answer the 5 short questions below to receive your recommended Durasteel system specifications. Hover over the ? icons for a brief explanation.

Question 1/5

Type of system required?

Question 2/5

Fire rating required?

Question 3/5

Fire integrity-only or integrity and insulation?

Question 4/5

Fire attack risk from one side or both sides of the system?

Question 5/5

Blast rating required in addition to fire rating?

Creating your results page

Thanks for completing the SpecUp, you’ll be redirected to your results shortly.

Click here if you aren't redirected after a few seconds

Start your project

Tell us about your project. Please complete this form. One of our sales team will come back to you with more details. If you prefer, you can drop us an email.





    Project details




    Attach any files that may assist us with your enquiry (specs, drawings, bill of quantities, etc.)

    Acceptable file types are .pdf, .jpg, .dwg, .xls, .xlsx, .doc, .docx, .zip and .rar up to a maximum of 15mb. For files larger than this, please use the external file upload link below.