For your information

You are being redirected to one of our divisional subsites which contains more detailed information on the required division. To navigate back to the main Invicta Group site, please click the link found in the footer at the bottom of the page.

Military Fire Escape Barrier

Larkhill, UK

Quick Quote

Call Benn Larkin Anand Raghavan Ben Tan Krishna Kumar Anand Raghavan Our USA Office on

Home Case Studies Military Fire Escape Barrier

Main Contractor

Morgan Sindall

End Client

MOD

Application

Fire Escape Barrier

Height

6m

Company profile

The Ministry of Defence (MOD) is the government department responsible for implementing the UK’s defence policy, and is the headquarters of the British Armed Forces. On a day-to-day basis, the MOD runs the armed forces, and undertakes contingency planning and defence procurement.

The MOD owns or retains the ‘right to access’ almost 550,000 hectares of land, equivalent to 1.8% of the UK’s total land mass. As a result, it is responsible for managing and maintaining hundreds of sites and facilities through its Defence Infrastructure Organisation arm, including airfields, barracks and depots.

Overview

Larkhill

Contractor Morgan Sindall approached us to provide a fire escape barrier for the Larkhill Royal School of Artillery, the primary training facility for Royal Artillery recruits and home to the Gunnery Training Team. This would provide protection for building occupants using the escape in the event of a major fire.

The barrier would have to be installed at roof level (a height of 6 metres), and would need to resist both fire and wind loads. As Larkhill is an extremely busy site – more than 100 years after it was built, it remains the army’s largest national training area – the work would need to be completed in a period of 3-4 days.

Technical Constraints

As well as negotiating the six metre height to roof level, our Durasteel engineers would also need to collaborate with a waterproofing team for the installation to be completed. As the building featured a waterproof roof system, pockets would have to be cut in the waterproofing system to expose the concrete slab. Once this slab was exposed, Durasteel engineers could then install the support steelwork.
The waterproofing specialists could then infill the pitch-pocket with the waterproofing system over the top of the support steelwork base plates. Finally, our Durasteel engineers could then finish installation of the Durasteel system – preventing any water ingress into the building structure.

Solution

Larkhill

Bearing the unique waterproofing and wind load requirements in mind, Invicta worked closely with an independent structural engineer. This ensured that we gave sufficient protection to the fire escape route from the roof light windows in the event of a fire breaking through the roof lights.

We also included bespoke structural steel work within the fire walls. This was manufactured off-site and galvanized, giving the wall more structural stability in both normal and fire conditions.

Result

The project was successfully completed in the allotted period by two Invicta Durasteel engineers, allowing the site to quickly be handed over for inspection and client handover.

The barrier was successfully installed, signed off and certificated to the highest possible standards, as per the design report and the client’s specifications. The final result provides the level of fire protection required to meet site conditions for this critical defence facility.

 

Share/Like this page

Accreditations & Affiliations