Project challenges

Invicta’s Durasteel division has recently completed the installation of four demountable UKPN (UK Power Networks, previously known as EDF Energy) blast barriers to give blast protection of up to 10kN/m² at a substation demolition site in London.

Technical constraints

Due to the limited working space on site, the 4 no 2.5 tonne Durasteel blast barriers were fully pre-fabricated and then lifted and secured into position using a crane. The blast barriers were designed and installed to protect personnel working on the demolition site from the potential explosions of four transformers located in the immediate vicinity.

Installed solution

The barriers are fully demountable within 4 hours in the event of a transformer failing, and the barrier requiring removal in order to allow access to the transformer.

End result

The project was completed from start to finish in less than 5 weeks, and the blast barriers comply with stringent UKPN specifications.

Accreditations & Affiliations

Safecontrator Logo
SafeContractor Approved
ASFP Logo
FORS Bronze

For your information

You are being redirected to one of our divisional subsites which contains more detailed information on the required division. To navigate back to the main Invicta Group site, please click the link found in the footer at the bottom of the page.